Direct Material Price Variance Calculator
Test cases replayed : 2 of 2 match · Methodology · No outside source listed
Enter the actual and standard price per unit of material, the quantity bought and used, and the standard quantity allowed for the output made.
Result
Price variance
Price variance is
- Quantity variance ($)
- Quantity variance is
- Total materials variance ($)
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Actual price per unit, in dollars: enter 0 or more.
- Standard price per unit, in dollars: enter 0 or more.
- Actual quantity purchased and used (units): enter 0 or more.
- Standard quantity allowed for actual output (units): enter 0 or more.
- Read the result: Price variance; the panel also shows Price variance is, Quantity variance ($), Quantity variance is and Total materials variance ($).
How this calculator works
Direct materials price variance = (actual price − standard price) × actual quantity. Quantity (usage) variance = (actual quantity − standard quantity allowed) × standard price. Positive values are unfavorable (cost more than standard), negative values favorable.
This calculator assumes the quantity purchased equals the quantity used. When they differ, compute the price variance on the quantity purchased and the quantity variance on the quantity used.
The formula
| Symbol | Meaning | Unit |
|---|---|---|
| Actual price per unit | $ | |
| Standard price per unit | $ | |
| Actual quantity purchased and used | units | |
| Price variance | $ |
Worked example
| Actual price per unit | $5.2 |
|---|---|
| Standard price per unit | $5 |
| Actual quantity purchased and used (units) | 10,000 |
| Standard quantity allowed for actual output (units) | 9,500 |
| Price variance is | Unfavorable |
|---|---|
| Quantity variance ($) | $2,500.00 |
| Quantity variance is | Unfavorable |
| Total materials variance ($) | $4,500.00 |
Price variance $2,000.00
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
Material standard is $5.00; we paid $5.20 for 10,000 units. What is the price variance?
$2,000.00, unfavorable. Using 10,000 units where 9,500 were allowed adds a $2,500.00 unfavorable quantity variance.
Is a favorable price variance always good?
Not always. Cheaper material can be lower quality and cause an unfavorable quantity variance through waste.