Enter the activity and total cost in the period with the highest activity and in the period with the lowest, then the activity level you want to estimate.
Result
Variable cost per unit
Fixed cost per period ($)
- Estimated total cost at that activity ($)
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Highest activity level (units): enter 0 or more.
- Total cost at the highest activity, in dollars: enter 0 or more.
- Lowest activity level (units): enter 0 or more.
- Total cost at the lowest activity, in dollars: enter 0 or more.
- Activity level to estimate (units): enter 0 or more.
- Read the result: Variable cost per unit; the panel also shows Fixed cost per period ($) and Estimated total cost at that activity ($).
How this calculator works
Variable cost per unit = (cost at highest activity − cost at lowest activity) ÷ (highest − lowest activity). Fixed cost = total cost at the highest activity − variable cost per unit × highest activity. Estimated cost = fixed cost + variable cost per unit × activity.
The high-low method of cost accounting uses only the two extreme periods, so pick them by activity, not by cost, and check that neither is unusual. A regression over all periods is more precise.
The formula
| Symbol | Meaning | Unit |
|---|---|---|
| Highest activity level | units | |
| Total cost at the highest activity | $ | |
| Lowest activity level | units | |
| Total cost at the lowest activity | $ | |
| Variable cost per unit | $ |
Worked example
| Highest activity level (units) | 12,000 |
|---|---|
| Total cost at the highest activity | $85,000 |
| Lowest activity level (units) | 7,000 |
| Total cost at the lowest activity | $60,000 |
| Activity level to estimate (units) | 10,000 |
| Fixed cost per period ($) | $25,000.00 |
|---|---|
| Estimated total cost at that activity ($) | $75,000.00 |
Variable cost per unit $5.00
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
How does the high-low method work?
It draws a straight line through the highest and lowest activity points. From 7,000 units at $60,000 to 12,000 units at $85,000, the variable cost is $5.00 a unit and the fixed cost $25,000.
What are the limits of the high-low method?
It ignores every other period and assumes costs behave in a straight line between the two points.