Test cases replayed : 2 of 2 match · Methodology · No outside source listed

Enter the number of workers, the hours each works per day and the number of days, plus the size of a job in labor hours to estimate its duration.

Result

Sample figures

Total man-hours—

Person-days —

  • Days to finish the job with this crew—

Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.

Man-Hours Calculator

Number of workers: enter 0 or more. Prefilled example: 5.

Hours worked per person per day: enter a number from 0 to 24. Prefilled example: 8.

Number of working days: enter 0 or more. Prefilled example: 10.

Size of a job to schedule (man-hours): enter 0 or more. Prefilled example: 1,000.

How to use this calculator

Fill in the fields in this order; each step takes you to its field.

  1. Number of workers: enter 0 or more.
  2. Hours worked per person per day: enter a number from 0 to 24.
  3. Number of working days: enter 0 or more.
  4. Size of a job to schedule (man-hours): enter 0 or more.
  5. Read the result: Total man-hours; the panel also shows Person-days and Days to finish the job with this crew.

How this calculator works

Man-hours = workers × hours per day × days. Days needed for a job = job size in man-hours ÷ (workers × hours per day).

This assumes every worker is equally productive and the work can be shared; on real projects, adding people does not always shorten the schedule in proportion.

The formula

  1. Mh=w×h×d
Symbols used in the formula
SymbolMeaning
wNumber of workers
hHours worked per person per day
dNumber of working days
MhTotal man-hours

Worked example

Number of workers5
Hours worked per person per day8
Number of working days10
Size of a job to schedule (man-hours)1,000
Person-days50
Days to finish the job with this crew25
  1. Mh=5×8×10=400

Total man-hours 400

Each step uses the unrounded value of the step before it; figures on this page are rounded for display.

Frequently asked questions

How do I calculate man-hours?

Multiply people by hours by days: 5 workers × 8 hours × 10 days = 400 man-hours.

How long does a 1,000 man-hour job take with 5 workers?

At 8 hours a day, 1,000 ÷ 40 = 25 working days.