Enter the upper and lower specification limits and the process mean and standard deviation to get the capability indices.
Result
Cpk, min(Cpu, Cpl)
Cp, (USL − LSL) ÷ 6σ
- Cpu, (USL − μ) ÷ 3σ
- Cpl, (μ − LSL) ÷ 3σ
- Expected out-of-spec parts per million (normal process)
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Upper specification limit (USL): enter a number.
- Lower specification limit (LSL): enter a number.
- Process mean (μ): enter a number.
- Process standard deviation (σ): enter 0 or more.
- Read the result: Cpk, min(Cpu, Cpl); the panel also shows Cp, (USL − LSL) ÷ 6σ, Cpu, (USL − μ) ÷ 3σ, Cpl, (μ − LSL) ÷ 3σ and Expected out-of-spec parts per million (normal process).
How this calculator works
Cp = (USL − LSL) ÷ 6σ compares the width of the specification with the natural spread of the process. Cpk = min[(USL − μ) ÷ 3σ, (μ − LSL) ÷ 3σ] also accounts for how far the mean is off centre; Cpk = Cp only when the process is centred.
These are the definitions of the NIST/SEMATECH e-Handbook of Statistical Methods (process capability). They assume a stable process with normally distributed output; the parts per million outside the limits are computed from the normal distribution with the given mean and σ.
With σ estimated from within-subgroup variation the indices are Cp and Cpk; with the overall standard deviation the same formulas are usually called Pp and Ppk.
The formula
| Symbol | Meaning |
|---|---|
| Upper specification limit (USL) | |
| Lower specification limit (LSL) | |
| Process mean | |
| Process standard deviation | |
| Cpu, (USL − μ) ÷ 3σ | |
| Cpl, (μ − LSL) ÷ 3σ | |
| Cpk, min(Cpu, Cpl) | |
min(a, b, …) | the smallest of the values. |
Worked example
| Upper specification limit (USL) | 10.5 |
|---|---|
| Lower specification limit (LSL) | 9.5 |
| Process mean (μ) | 10.1 |
| Process standard deviation (σ) | 0.12 |
| Cp, (USL − LSL) ÷ 6σ | 1.3889 |
|---|---|
| Cpu, (USL − μ) ÷ 3σ | 1.1111 |
| Cpl, (μ − LSL) ÷ 3σ | 1.6667 |
| Expected out-of-spec parts per million (normal process) | 429 |
Cpk, min(Cpu, Cpl) 1.1111
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
What is a good Cpk?
Values of 1.33 or more are a common requirement, and 1.0 means the nearer limit sits exactly 3σ from the mean; the target is set by the customer or industry.
Why is Cpk lower than Cp here?
The mean 10.1 is closer to the upper limit 10.5 than to the lower limit 9.5, so the upper side sets Cpk = 0.4 ÷ 0.36 ≈ 1.1111 while Cp ≈ 1.3889.