Cycle Time Calculator

Test cases replayed : 2 of 2 match · Methodology · No outside source listed

Enter the production time, the downtime in that period and the number of good units made.

Result

Sample figures

Cycle time (minutes per unit)—

Net production time (minutes) —

  • Cycle time (seconds per unit)—
  • Units per hour—

Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.

Cycle Time Calculator

Production time, in minutes: enter 0 or more. Prefilled example: 480.

Downtime and breaks, in minutes: enter 0 or more. Prefilled example: 30.

Units produced: enter 1 or more. Prefilled example: 225.

How to use this calculator

Fill in the fields in this order; each step takes you to its field.

  1. Production time, in minutes: enter 0 or more.
  2. Downtime and breaks, in minutes: enter 0 or more.
  3. Units produced: enter 1 or more.
  4. Read the result: Cycle time (minutes per unit); the panel also shows Net production time (minutes), Cycle time (seconds per unit) and Units per hour.

How this calculator works

Average cycle time = net production time ÷ units produced, where net production time = scheduled time − downtime and breaks. Units per hour = units ÷ net hours.

Cycle time is what the process actually achieves; takt time (available time ÷ customer demand) is the pace it must keep. A cycle time longer than takt means demand is not met.

The formula

  1. Net=av−dn
  2. Ct=Netu
Symbols used in the formula
SymbolMeaningUnit
avProduction timeminutes
dnDowntime and breaksminutes
uUnits produced
NetNet production timeminutes
CtCycle timeminutes per unit

Worked example

Production time480 minutes
Downtime and breaks30 minutes
Units produced225
Net production time (minutes)450
Cycle time (seconds per unit)120.0
Units per hour30.0
  1. Net=480−30=450
  2. Ct=450225=2

Cycle time (minutes per unit) 2.00

Each step uses the unrounded value of the step before it; figures on this page are rounded for display.

Frequently asked questions

What is the cycle time for 225 units in an 8-hour shift with 30 minutes of downtime?

450 ÷ 225 = 2.00 minutes (120 seconds) per unit, or 30.0 units an hour.

What is the difference between cycle time and takt time?

Cycle time measures how long a unit actually takes; takt time is how often one must be finished to match demand.