Earned Value Management Calculator

Test cases replayed : 2 of 2 match · Methodology · No outside source listed

Enter the budget at completion, planned value, earned value and actual cost at the status date to get the standard earned value indicators.

Result

Sample figures

Cost performance index, CPI = EV ÷ AC—

Schedule performance index, SPI = EV ÷ PV —

  • Estimate at completion, EAC = BAC ÷ CPI ($)—
  • Cost variance, CV = EV − AC ($)—
  • Schedule variance, SV = EV − PV ($)—
  • Estimate to complete, ETC = EAC − AC ($)—
  • Variance at completion, VAC = BAC − EAC ($)—

Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.

Earned Value Management Calculator

Budget at completion, BAC, in dollars: enter 0 or more. Prefilled example: 100,000.

Planned value, PV, in dollars: enter 0 or more. Prefilled example: 50,000.

Earned value, EV, in dollars: enter 0 or more. Prefilled example: 40,000.

Actual cost, AC, in dollars: enter 0 or more. Prefilled example: 45,000.

How to use this calculator

Fill in the fields in this order; each step takes you to its field.

  1. Budget at completion, BAC, in dollars: enter 0 or more.
  2. Planned value, PV, in dollars: enter 0 or more.
  3. Earned value, EV, in dollars: enter 0 or more.
  4. Actual cost, AC, in dollars: enter 0 or more.
  5. Read the result: Cost performance index, CPI = EV ÷ AC; the panel also shows Cost variance, CV = EV − AC ($), Schedule variance, SV = EV − PV ($), Schedule performance index, SPI = EV ÷ PV, Estimate at completion, EAC = BAC ÷ CPI ($), Estimate to complete, ETC = EAC − AC ($) and Variance at completion, VAC = BAC − EAC ($).

How this calculator works

Earned value management, as set out in PMI's PMBOK Guide: cost variance CV = EV − AC, schedule variance SV = EV − PV, CPI = EV ÷ AC, SPI = EV ÷ PV. Values below 0 (variances) or below 1 (indices) mean over budget or behind schedule.

Estimate at completion here assumes the cost performance so far continues: EAC = BAC ÷ CPI. ETC = EAC − AC and VAC = BAC − EAC.

The formula

  1. Cpi=evac
Symbols used in the formula
SymbolMeaningUnit
evEarned value, EV$
acActual cost, AC$
CpiCost performance index, CPI = EV ÷ AC

Worked example

Budget at completion, BAC$100,000
Planned value, PV$50,000
Earned value, EV$40,000
Actual cost, AC$45,000
Cost variance, CV = EV − AC ($)-$5,000
Schedule variance, SV = EV − PV ($)-$10,000
Schedule performance index, SPI = EV ÷ PV0.8
Estimate at completion, EAC = BAC ÷ CPI ($)$112,500
Estimate to complete, ETC = EAC − AC ($)$67,500
Variance at completion, VAC = BAC − EAC ($)-$12,500
  1. Cpi=40,00045,000=0.888889

Cost performance index, CPI = EV ÷ AC 0.8889

Each step uses the unrounded value of the step before it; figures on this page are rounded for display.

Frequently asked questions

With BAC $100,000, PV $50,000, EV $40,000 and AC $45,000, how is the project doing?

CPI is 0.8889 and SPI 0.8: over budget and behind schedule. At this pace it would finish at $112,500.

What is earned value?

The budgeted cost of the work actually done: percent complete × budget at completion.