Earned Value Management Calculator
Test cases replayed : 2 of 2 match · Methodology · No outside source listed
Enter the budget at completion, planned value, earned value and actual cost at the status date to get the standard earned value indicators.
Result
Cost performance index, CPI = EV ÷ AC
Schedule performance index, SPI = EV ÷ PV
- Estimate at completion, EAC = BAC ÷ CPI ($)
- Cost variance, CV = EV − AC ($)
- Schedule variance, SV = EV − PV ($)
- Estimate to complete, ETC = EAC − AC ($)
- Variance at completion, VAC = BAC − EAC ($)
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Budget at completion, BAC, in dollars: enter 0 or more.
- Planned value, PV, in dollars: enter 0 or more.
- Earned value, EV, in dollars: enter 0 or more.
- Actual cost, AC, in dollars: enter 0 or more.
- Read the result: Cost performance index, CPI = EV ÷ AC; the panel also shows Cost variance, CV = EV − AC ($), Schedule variance, SV = EV − PV ($), Schedule performance index, SPI = EV ÷ PV, Estimate at completion, EAC = BAC ÷ CPI ($), Estimate to complete, ETC = EAC − AC ($) and Variance at completion, VAC = BAC − EAC ($).
How this calculator works
Earned value management, as set out in PMI's PMBOK Guide: cost variance CV = EV − AC, schedule variance SV = EV − PV, CPI = EV ÷ AC, SPI = EV ÷ PV. Values below 0 (variances) or below 1 (indices) mean over budget or behind schedule.
Estimate at completion here assumes the cost performance so far continues: EAC = BAC ÷ CPI. ETC = EAC − AC and VAC = BAC − EAC.
The formula
| Symbol | Meaning | Unit |
|---|---|---|
| Earned value, EV | $ | |
| Actual cost, AC | $ | |
| Cost performance index, CPI = EV ÷ AC |
Worked example
| Budget at completion, BAC | $100,000 |
|---|---|
| Planned value, PV | $50,000 |
| Earned value, EV | $40,000 |
| Actual cost, AC | $45,000 |
| Cost variance, CV = EV − AC ($) | -$5,000 |
|---|---|
| Schedule variance, SV = EV − PV ($) | -$10,000 |
| Schedule performance index, SPI = EV ÷ PV | 0.8 |
| Estimate at completion, EAC = BAC ÷ CPI ($) | $112,500 |
| Estimate to complete, ETC = EAC − AC ($) | $67,500 |
| Variance at completion, VAC = BAC − EAC ($) | -$12,500 |
Cost performance index, CPI = EV ÷ AC 0.8889
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
With BAC $100,000, PV $50,000, EV $40,000 and AC $45,000, how is the project doing?
CPI is 0.8889 and SPI 0.8: over budget and behind schedule. At this pace it would finish at $112,500.
What is earned value?
The budgeted cost of the work actually done: percent complete × budget at completion.