Find how often one unit must be finished to meet demand: net available working time divided by the units customers need.

Result

Sample figures

Takt time (seconds per unit)—

Net available time per day (minutes) —

  • Takt time (minutes per unit)—
  • Required output (units per hour)—

Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.

Takt Time Calculator

Shift length, in minutes: enter 0 or more. Prefilled example: 480.

Planned breaks and stops per shift, in minutes: enter 0 or more. Prefilled example: 30.

Shifts per day: enter 1 or more. Prefilled example: 2.

Customer demand (units per day): enter 1 or more. Prefilled example: 900.

How to use this calculator

Fill in the fields in this order; each step takes you to its field.

  1. Shift length, in minutes: enter 0 or more.
  2. Planned breaks and stops per shift, in minutes: enter 0 or more.
  3. Shifts per day: enter 1 or more.
  4. Customer demand (units per day): enter 1 or more.
  5. Read the result: Takt time (seconds per unit); the panel also shows Net available time per day (minutes), Takt time (minutes per unit) and Required output (units per hour).

How this calculator works

Takt time = net available production time ÷ customer demand over the same period. It is the lean manufacturing (Toyota Production System) measure of the pace a line must keep.

Net available time = (shift length − planned breaks and stops) × shifts. Unplanned downtime is not subtracted: it is what the line must absorb.

The formula

  1. A=(sh−br)×n
  2. T=A×60dem
Symbols used in the formula
SymbolMeaningUnit
shShift lengthminutes
brPlanned breaks and stops per shiftminutes
nShifts per day
demCustomer demandunits per day
ANet available time per dayminutes
TTakt timeseconds per unit

Worked example

Shift length480 minutes
Planned breaks and stops per shift30 minutes
Shifts per day2
Customer demand (units per day)900
Net available time per day (minutes)900
Takt time (minutes per unit)1
Required output (units per hour)60
  1. A=(480−30)×2=900
  2. T=900×60900=60

Takt time (seconds per unit) 60

Each step uses the unrounded value of the step before it; figures on this page are rounded for display.

Frequently asked questions

Is takt time the same as cycle time?

No. Takt time is the pace demand requires; cycle time is how long the process actually takes per unit. A cycle time above takt time means demand is not met.

What is the takt time for two 480-minute shifts with 30 minutes of breaks and 900 units a day?

900 minutes = 54,000 seconds ÷ 900 units = 60 seconds per unit.