Turn optimistic, most likely and pessimistic estimates into the PERT expected time and its spread.

Result

Sample figures

Expected time, (O + 4M + P) ÷ 6—

Standard deviation, (P − O) ÷ 6 —

  • Variance—
  • Expected time − 2 standard deviations—
  • Expected time + 2 standard deviations—

Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.

PERT Calculator

Optimistic estimate (days or any unit): enter 0 or more. Prefilled example: 4.

Most likely estimate: enter 0 or more. Prefilled example: 6.

Pessimistic estimate: enter 0 or more. Prefilled example: 14.

How to use this calculator

Fill in the fields in this order; each step takes you to its field.

  1. Optimistic estimate (days or any unit): enter 0 or more.
  2. Most likely estimate: enter 0 or more.
  3. Pessimistic estimate: enter 0 or more.
  4. Read the result: Expected time, (O + 4M + P) ÷ 6; the panel also shows Standard deviation, (P − O) ÷ 6, Variance, Expected time − 2 standard deviations and Expected time + 2 standard deviations.

How this calculator works

The Program Evaluation and Review Technique (PERT), developed for the US Navy in 1958, weights the most likely estimate four times: expected time E = (O + 4M + P) ÷ 6, with standard deviation σ = (P − O) ÷ 6.

For a chain of tasks, add the expected times and add the variances (σ²), then take the square root for the chain's standard deviation. E ± 2σ covers roughly 95% of outcomes under a normal approximation.

The formula

  1. E=o+4×m+p6
Symbols used in the formula
SymbolMeaningUnit
oOptimistic estimatedays or any unit
mMost likely estimate
pPessimistic estimate
EExpected time, (O + 4M + P) ÷ 6

Worked example

Optimistic estimate (days or any unit)4
Most likely estimate6
Pessimistic estimate14
Standard deviation, (P − O) ÷ 61.6667
Variance2.7778
Expected time − 2 standard deviations3.6667
Expected time + 2 standard deviations10.3333
  1. E=4+4×6+146=7

Expected time, (O + 4M + P) ÷ 6 7

Each step uses the unrounded value of the step before it; figures on this page are rounded for display.

Frequently asked questions

What is the PERT formula?

Expected time = (optimistic + 4 × most likely + pessimistic) ÷ 6: with 4, 6 and 14 days, (4 + 24 + 14) ÷ 6 = 7 days.

How is PERT different from a simple average?

A simple average of the three estimates gives them equal weight; PERT counts the most likely estimate four times, so it stays closer to it.