PERT Calculator
Test cases replayed : 2 of 2 match · Methodology · No outside source listed
Turn optimistic, most likely and pessimistic estimates into the PERT expected time and its spread.
Result
Expected time, (O + 4M + P) ÷ 6
Standard deviation, (P − O) ÷ 6
- Variance
- Expected time − 2 standard deviations
- Expected time + 2 standard deviations
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Optimistic estimate (days or any unit): enter 0 or more.
- Most likely estimate: enter 0 or more.
- Pessimistic estimate: enter 0 or more.
- Read the result: Expected time, (O + 4M + P) ÷ 6; the panel also shows Standard deviation, (P − O) ÷ 6, Variance, Expected time − 2 standard deviations and Expected time + 2 standard deviations.
How this calculator works
The Program Evaluation and Review Technique (PERT), developed for the US Navy in 1958, weights the most likely estimate four times: expected time E = (O + 4M + P) ÷ 6, with standard deviation σ = (P − O) ÷ 6.
For a chain of tasks, add the expected times and add the variances (σ²), then take the square root for the chain's standard deviation. E ± 2σ covers roughly 95% of outcomes under a normal approximation.
The formula
| Symbol | Meaning | Unit |
|---|---|---|
| Optimistic estimate | days or any unit | |
| Most likely estimate | ||
| Pessimistic estimate | ||
| Expected time, (O + 4M + P) ÷ 6 |
Worked example
| Optimistic estimate (days or any unit) | 4 |
|---|---|
| Most likely estimate | 6 |
| Pessimistic estimate | 14 |
| Standard deviation, (P − O) ÷ 6 | 1.6667 |
|---|---|
| Variance | 2.7778 |
| Expected time − 2 standard deviations | 3.6667 |
| Expected time + 2 standard deviations | 10.3333 |
Expected time, (O + 4M + P) ÷ 6 7
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
What is the PERT formula?
Expected time = (optimistic + 4 × most likely + pessimistic) ÷ 6: with 4, 6 and 14 days, (4 + 24 + 14) ÷ 6 = 7 days.
How is PERT different from a simple average?
A simple average of the three estimates gives them equal weight; PERT counts the most likely estimate four times, so it stays closer to it.