Reorder Point Calculator
Test cases replayed : 2 of 2 match · Methodology · No outside source listed
Enter your average daily sales, the supplier's lead time and your safety stock to get the reorder point.
Result
Reorder point (units)
Demand during lead time (units)
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Average demand (units per day): enter 0 or more.
- Lead time, in days: enter 0 or more.
- Safety stock (units): enter 0 or more.
- Read the result: Reorder point (units); the panel also shows Demand during lead time (units).
How this calculator works
Reorder point = average daily demand × lead time in days + safety stock. When stock on hand falls to this level, an order placed now should arrive just as the safety stock is reached.
Safety stock covers demand and delivery variation; a common way to size it is a service-level factor times the standard deviation of demand over the lead time.
The formula
| Symbol | Meaning | Unit |
|---|---|---|
| Average demand | units per day | |
| Lead time | days | |
| Safety stock | units | |
| Demand during lead time | units | |
| Reorder point | units |
Worked example
| Average demand (units per day) | 40 |
|---|---|
| Lead time | 7 days |
| Safety stock (units) | 100 |
| Demand during lead time (units) | 280 |
|---|
Reorder point (units) 380
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
What is the reorder point for 40 units a day, 7 days lead time and 100 units of safety stock?
380 units: 280 for the lead time plus 100 in reserve.
Does the reorder point tell me how much to order?
No. It tells you when; the order size comes from a separate rule such as economic order quantity.