Slack Time Calculator
Test cases replayed : 2 of 2 match · Methodology · No outside source listed
Enter the task's earliest and latest start, its duration and the earliest start of the task that follows it, in the same time unit (days).
Result
Total float (slack) = LS − ES
Earliest finish, EF = ES + duration
- Latest finish, LF = LS + duration
- Free float = next ES − EF
- On the critical path?
Estimate for planning only, not tax, legal, financial or medical advice. This calculator uses the method explained on this page.
This browser did not allow copying. The sentence is in the box below, already selected: copy it with your keyboard or the menu.
How to use this calculator
Fill in the fields in this order; each step takes you to its field.
- Earliest start, ES (day): enter 0 or more.
- Latest start, LS (day): enter 0 or more.
- Duration, in days: enter 0 or more.
- Earliest start of the next task (day): enter 0 or more.
- Read the result: Total float (slack) = LS − ES; the panel also shows Earliest finish, EF = ES + duration, Latest finish, LF = LS + duration, Free float = next ES − EF and On the critical path?.
How this calculator works
In the critical path method (CPM), total float or slack = latest start − earliest start (= latest finish − earliest finish): how long the task can slip without delaying the project end.
Free float = earliest start of the following task − this task's earliest finish: how long it can slip without delaying any other task. A task with zero total float is on the critical path.
The formula
| Symbol | Meaning | Unit |
|---|---|---|
| Earliest start, ES | day | |
| Latest start, LS | day | |
| Total float (slack) = LS − ES |
Worked example
| Earliest start, ES (day) | 4 |
|---|---|
| Latest start, LS (day) | 9 |
| Duration | 6 days |
| Earliest start of the next task (day) | 12 |
| Earliest finish, EF = ES + duration | 10 |
|---|---|
| Latest finish, LF = LS + duration | 15 |
| Free float = next ES − EF | 2 |
| On the critical path? | No |
Total float (slack) = LS − ES 5
Each step uses the unrounded value of the step before it; figures on this page are rounded for display.
Frequently asked questions
A task with ES 4, LS 9 and 6 days of work: what is its slack?
5 days of total float; if the next task can start on day 12, its free float is 2 days.
Can slack be negative?
Yes: when a deadline is earlier than the schedule allows, latest dates come before earliest ones and the plan must be shortened.